Task       Yr 1 Yr 2 Yr 3
No. Task List Wk Mo Q 1 Q 2 Q 3 Q 4 Q 1 Q 2 Q 3 Q 4 Q 1 Q 2 Q 3 Q 4
70 Review and understand system 8 2 ]]]]  
80 Review SDU functions in Counties and states 8 2 ]]]]
90 Determine transaction volumes by type, by county 3 0.75     ]]
100 Determine statewide storage requirements 3 0.75     ]]
110 Design statewide Internet Architecture for CSE 12 3      ]]]]]]
150 Design Data warehouse strategy 4 1          ]]
160 Design Internet front-end applications 8 2          ]]]]
170 Design SDU functions 12 3          ]]]]
180 Design data conversion strategy 8 2        ]]]]
190 Develop on-line training and help functions 24 6        ]]]]]]]]]]]]]
200 Develop system conversion and implementation plan 12 3        ]]]]]]
210 Develop SDU conversion and implementation plan 12 3        ]]]]]]
220 Develop Internet front-end 12 3        ]]]]]]
230 Test the Internet front-end 12 3             ]]]]]]      
240 Develop SDU functions 12 3        ]]]]]]
250 Test SDU functions 12 3        ]]]]]]
260 Test SDU conversion 8 2     ]]]]
270 Test system conversion 8 2     ]]]]
280 Install the web-enabled system at data center. 2 0.5          ]]
290 Install production SDU functions 2 0.5          ]]
300 Install hwr/swr/com based on the plan 24 6     ]]]]]]]]]]]]
310 Train county staff 70 17        ]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]
320 System implementation based on the plan 74 18         ]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]
330 Begin SDU functions as each county goes on line 74 18         ]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]
340 Project Management/Administration 156 36 ]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]]